What slow-paying owners and margin fade cost your cash.

A construction cash flow calculator for general contractors. Set your annual revenue, choose how much later owners pay and how much margin fades, and see the change in your year-end cash against plan.

The formula

  • Cash tied up by slower owners = annual revenue ÷ 365 × extra days
  • Less the share passed to subcontractors under pay-when-paid
  • Cash lost to fade = annual revenue × points of fade

An example

A $120M contractor whose owners pay 15 days later has about $120M ÷ 365 × 15 ≈ $4.9M more tied up in receivables. If about two thirds of that delay passes to subcontractors, the net hit is about $1.7M. One point of fade on top costs another $1.2M.

Cash scenario

Run a cash scenario on your own numbers.

Set your revenue, then pick what goes wrong. The arithmetic shows how much less cash you would end the year with, and how much pay-when-paid gives back.

Owners pay
Margin fades by

With owners paying as usual and no fade, $400M of revenue ends the year on plan.

Arithmetic on your revenue, not a forecast. Owners pay as usual. No fade.

dideh runs this week by week on your own jobs, owners and subcontracts.

See the cash forecast

How it works

Three lines of arithmetic.

The result is the cash you would be short at year end, compared with a plan where owners pay as usual and every job finishes at its bid margin. Change any input and the address updates, so you can share the case you ran. Terms like fade, retainage and pay-when-paid are defined in the construction finance glossary.

  1. 01

    Slower pay

    Revenue ÷ 365 × days later

    When owners pay later, a slice of a year’s billing sits in receivables instead of the bank. On $400M of revenue, every day later holds up about $1.1M.

  2. 02

    Pay-when-paid

    Slower pay × about two thirds

    If your subcontracts are pay-when-paid, you pay subcontractors when the owner pays you, so part of the delay passes on to them. The calculator assumes about two thirds; your share depends on how much of your cost is subcontracted.

  3. 03

    Margin fade

    Revenue × points of fade

    Fade is margin lost between the bid and the final result. Each point of fade on $400M of revenue is $4M that never arrives as cash.

FAQ

About the calculator

If yours isn’t here, bring it to the walkthrough.

What does this calculator show?

How much less cash a general contractor would end the year with if owners paid later than usual and margins faded, against a plan where neither happens. It is simple arithmetic on your annual revenue, not a forecast of your business.

Why does pay-when-paid reduce the hit?

Under pay-when-paid terms you pay subcontractors when the owner pays you, so a slower owner also slows part of what you owe. The calculator assumes about two thirds of a delay passes to subcontractors; your own share depends on how much of your cost is subcontracted and how your subcontracts are written.

What does the calculator leave out?

Retainage, billing timing within the month, how the delay spreads across jobs and owners, the cost of borrowing on your line, and how fade shows up over the life of each job. A cash forecast built from your own jobs, owners and subcontracts captures those; this page shows the order of magnitude.

How does dideh forecast cash instead?

Week by week for 13 and 26 weeks, from every job’s schedule, cost to complete, billing terms, retainage and pay-when-paid, with the low point against your cash minimum and stress tests for slower-paying owners.

Walkthrough

See dideh run a modeled contractor.

We’ll walk you through a fully modeled general contractor, with WIP, pay-when-paid cash, governed questions and the specialist team in simulation. Then we’ll talk through your systems and what a first phase would cover.

Prefer email? Write to hello@dideh.ai.

We use these details only to arrange the walkthrough.