Retainage calculator
How much of your cash is sitting in retainage?
A retainage calculator for general contractors. Enter a job’s contract, billings, owner retainage terms and what you hold from subcontractors, and see the net retainage your own working capital is funding.
The formula
- Owner retainage = each billing × the retainage rate in force
- Subcontractor retainage = each sub billing × the rate you hold
- Net retainage you fund = owner retainage − subcontractor retainage
An example
You have billed $4M at 10% retainage, so the owner is holding $400K. Your subcontractors have billed you $3M and you hold 10%, or $300K. The net $100K is retainage your own working capital is funding until the owner releases it.
Retainage calculator
Enter one job.
Take the terms from your owner contract and subcontract agreements. The example is an illustration: a $60M job at 10% retainage, dropping to 5% at half complete.
Revised contract, $M
Gross work billed so far, $M
Held on each payment
Same as above if it never drops
Your sub agreements
Net retainage, your cash
$2.0M
of your own cash tied up in retainage: held by the owner and not offset by what you hold from subs.
- Held by owner
- $3.6M
- You hold from subs
- $1.6M
- Effective rate
- 8.6%
- Owner holds at finish
- $4.5M
The owner holds $3.6M, an effective 8.6% of billings. You hold $1.6M from subs. The gap is funded from your working capital until the owner releases it, often months after substantial completion. Track it in your cash forecast by job and expected release date, and push for reduction at 50% complete where the contract allows it.
Arithmetic on your inputs, not a forecast. Held by owner: $30.0M × 10.0% + $12.0M × 5.0%. Held from subs: $42.0M × 75% × 5.0%. Assumes the lower rate applies to billings after half the contract, with no retainage released yet.
dideh forecasts retainage release by job in the cash forecast.
See cash forecastingReading the result
The release date matters as much as the amount.
Retainage receivable is earned cash with a date on it, and that date is usually later than planned: punch lists, closeout documents and the owner’s own approvals push release months past substantial completion. Add it up across every open job and it is often the largest single block of cash a contractor is waiting on.
Put each job’s retainage into your 13-week cash flow forecast as its own line, and see what slow-paying owners cost over a year with the cash flow calculator.
FAQ
About the calculator
If yours isn’t here, bring it to the walkthrough.
What is retainage in construction?
Retainage, or retention, is a percentage of each progress payment that the owner holds back until the job, or a defined stage of it, is complete. It is usually 5% to 10%. General contractors normally hold back a similar percentage from their subcontractors.
How do you calculate retainage?
Multiply each amount billed by the retainage rate. If the rate drops partway through, often from 10% to 5% at 50% complete, apply the first rate to billings up to that point and the lower rate after it. The total is what the owner is holding.
Why net it against subcontractor retainage?
Retainage you hold from subcontractors is cash you have not yet paid out, so it offsets what the owner holds from you. The difference is what your own working capital is funding. It is usually largest on self-performed work and at the end of a job, when subs ask for their retainage before the owner releases yours.
What does the calculator leave out?
Partial releases, state prompt-payment and retainage laws, different rates by subcontract and the timing of release. In a cash forecast, retainage belongs as its own receipt by job with an expected release date.