Is this job overbilled or underbilled?

An over and under billing calculator for general contractors. Enter a job’s contract value, estimated total cost, cost to date and billings, and see its percent complete, earned revenue and billing position under percentage of completion.

The formula

  • Percent complete = cost to date ÷ estimated total cost
  • Earned revenue = percent complete × contract value
  • Over (under) billing = billed to date − earned revenue

An example

A $5M job with an estimated total cost of $4.2M has $1.68M of cost to date, so it is 40% complete and has earned $2.0M. It has billed $2.3M, so it is overbilled by $300K. Had it billed $1.8M, it would be underbilled by $200K.

Billing calculator

Enter one job.

Take the numbers from your job cost report and last pay application. The example is an illustration: a $40M job estimated at $35M of cost.

Original contract plus approved changes, $M

Cost to date plus cost to complete, $M

Job cost posted so far, $M

Gross billings, before retainage, $M

Billed against earned revenue

$1.2M

overbilled: billed ahead of the work, about 7% more than earned to date.

Percent complete
40.0%
Earned revenue
$16.0M
Projected margin
12.5%
Gross profit to date
$2.0M

Overbilling is a liability, not cash you have earned: it is work you still owe the owner. A little is normal on a front-loaded schedule of values. A lot, or a growing amount, can mean cash that will be needed to finish the job has already been spent, or that cost to complete is understated.

Arithmetic on your inputs, using the cost-to-cost method. Percent complete: $14.0M ÷ $35.0M. Earned revenue: $40.0M × 40.0%. Over or under billing: $17.2M billed less $16.0M earned.

dideh keeps every open job’s WIP position current, every week.

See the zero-day close

Reading the result

The estimate decides the answer.

Percent complete comes from cost to date over estimated total cost, so a cost to complete that has not been updated makes a job look further along, and better billed, than it is. Update the estimate first, then read the billing position.

Run it for every open job on your WIP schedule, or use the free template, which does this for every job at once. For what each position means to your bank and surety, read over and under billing explained.

FAQ

About the calculator

If yours isn’t here, bring it to the walkthrough.

What is over and under billing?

It is the gap between what a contractor has billed on a job and the revenue it has earned under percentage of completion. Billed more than earned is overbilling, a liability on the balance sheet. Earned more than billed is underbilling, an asset. Both are reported job by job on the WIP schedule.

How is it calculated?

Percent complete is cost to date divided by estimated total cost. Earned revenue is the contract value times percent complete. Over or under billing is billed to date minus earned revenue: a positive result is overbilled, a negative result is underbilled.

Is overbilling good or bad?

Modest overbilling is common and helps cash flow, because the owner is funding the work ahead of cost. Large or growing overbilling can mean the cash needed to finish the job has already been spent, or that the cost to complete is understated. Persistent underbilling usually points to unbilled change orders or an estimate that is creeping up.

What does the calculator leave out?

Uninstalled materials, unapproved change orders, retainage and any loss provision on a job projected to lose money. It uses the cost-to-cost method on the numbers you enter, so its answer is only as good as the estimate of cost to complete.

Walkthrough

See dideh run a modeled contractor.