Over and under billing, explained.
By Sina Ahmadi, Founder of dideh · Published
The short answer
Over or under billing is the gap between what a job has billed and the revenue it has earned under percentage of completion. Overbilling (billings in excess of costs and estimated earnings) is billing ahead of the work and is a liability; underbilling (costs and estimated earnings in excess of billings) is work done but not yet billed and is an asset. Moderate overbilling funds the work. Underbilling ties up cash, and when it grows it is often a sign of unapproved scope or an estimate that is too low.
How it is calculated
Start with earned revenue: revised contract × percent complete, where percent complete is cost to date ÷ estimated total cost. Then subtract earned revenue from billed to date. To run it on one of your own jobs, use the over/under billing calculator.
- Positive result: overbilled. You have billed more than you have earned. On the balance sheet it is a liability, billings in excess of costs and estimated earnings.
- Negative result: underbilled. You have earned more than you have billed. It is an asset, costs and estimated earnings in excess of billings.
| Overbilled | Underbilled | |
|---|---|---|
| Revised contract | $20.0M | $20.0M |
| Percent complete | 40% | 40% |
| Earned revenue | $8.0M | $8.0M |
| Billed to date | $8.6M | $7.2M |
| Over / (under) billed | $0.6M | ($0.8M) |
Why it matters for cash
Overbilling means the owner has funded part of the work in advance, which is why many contractors aim to stay modestly overbilled. Underbilling means you have paid for work the owner has not been asked to pay for yet. On a large job, a few points of underbilling can be millions of dollars of cash tied up, which then shows up in the 13-week cash forecast as a lower low point.
What causes underbilling
- Work done on pending change orders that cannot be billed until the owner signs.
- A schedule of values that back-loads billing relative to when cost is spent.
- Stored materials or early subcontractor costs not yet billable under the contract.
- An estimated total cost that is too low, which overstates percent complete and earned revenue. In that case the underbilling is really fade that has not been recognized.
When overbilling is a warning
Overbilling is usually a sign of good billing discipline. It becomes a warning when it is large on a job close to completion, because the cash has been collected but the cost to finish has not been paid, or when it hides costs that have been incurred but not yet recorded. Sureties look at whether overbillings are backed by cash on hand.
How lenders and sureties read it
Because underbilling is an asset, it adds to earnings and working capital. Lenders and sureties often discount it, and they watch net underbilling across the company closely. Persistent or growing underbilling on the same jobs is one of the first things they ask about.
A monthly check
- Update estimated total cost on every job before calculating billing position.
- List every underbilled job with the reason, and the date it will be billed.
- Escalate pending change orders behind the largest underbillings.
- Check that large overbillings are backed by cash, not spent on other jobs.
The free WIP schedule template calculates over and under billing for every job automatically.
How dideh does it
dideh calculates billing position for every job from the work itself, links underbilling to the change orders and estimates behind it, and carries it into the cash forecast. See the zero-day close.