What are billings in excess of costs and estimated earnings?

Also called: Overbilling, contract liability

The short answer

The amount billed on a job beyond the revenue earned to date under percentage of completion. It is a liability on the balance sheet: cash or receivables the contractor holds for work not yet done.

An example

A $5M job is 40% complete, so it has earned $2M of revenue. The contractor has billed $2.3M. The $300K difference is billings in excess, also called overbilling, and it sits on the balance sheet as a liability.

Why it matters to a general contractor

Some overbilling is healthy: it means the job is funding itself. Too much can hide trouble, because the cash has been collected for work the contractor still has to pay for. Sureties compare total overbillings with cash on hand.

Walkthrough

See dideh run a modeled contractor.

We’ll walk you through a fully modeled general contractor, with WIP, pay-when-paid cash, governed questions and the specialist team in simulation. Then we’ll talk through your systems and what a first phase would cover.

Prefer email? Write to hello@dideh.ai.

We use these details only to arrange the walkthrough.