What are costs and estimated earnings in excess of billings?
Also called: Underbilling, contract asset
The short answer
Revenue earned on a job under percentage of completion that has not yet been billed. It is an asset on the balance sheet, but one that has not turned into a receivable or cash, so lenders and sureties watch it closely.
An example
A $5M job is 60% complete, so it has earned $3M. The contractor has billed only $2.6M. The $400K difference is costs in excess, or underbilling: an asset on the balance sheet, but not yet a receivable or cash.
Why it matters to a general contractor
Underbilling means the contractor is funding the job from its own cash. Persistent or growing underbillings can also mean revenue is being recognized for work the owner won't pay for, which is why sureties and lenders look at them closely.