What are costs and estimated earnings in excess of billings?

Also called: Underbilling, contract asset

The short answer

Revenue earned on a job under percentage of completion that has not yet been billed. It is an asset on the balance sheet, but one that has not turned into a receivable or cash, so lenders and sureties watch it closely.

An example

A $5M job is 60% complete, so it has earned $3M. The contractor has billed only $2.6M. The $400K difference is costs in excess, or underbilling: an asset on the balance sheet, but not yet a receivable or cash.

Why it matters to a general contractor

Underbilling means the contractor is funding the job from its own cash. Persistent or growing underbillings can also mean revenue is being recognized for work the owner won't pay for, which is why sureties and lenders look at them closely.

Walkthrough

See dideh run a modeled contractor.

We’ll walk you through a fully modeled general contractor, with WIP, pay-when-paid cash, governed questions and the specialist team in simulation. Then we’ll talk through your systems and what a first phase would cover.

Prefer email? Write to hello@dideh.ai.

We use these details only to arrange the walkthrough.