What is over and under billing in construction?

The short answer

The gap between what has been billed on a job and the revenue earned under percentage of completion. Overbilling is billing ahead of the work; underbilling is work done but not yet billed. Both appear on the WIP schedule.

An example

Job A: earned $2.0M, billed $2.3M, so it is overbilled $300K. Job B: earned $3.0M, billed $2.6M, so it is underbilled $400K. Earned revenue is percent complete times contract value.

Why it matters to a general contractor

Over and under billing ties the WIP schedule to the balance sheet and to cash. Large underbillings are a warning sign for sureties; large overbillings mean cash collected for work still to be paid for.

Walkthrough

See dideh run a modeled contractor.

We’ll walk you through a fully modeled general contractor, with WIP, pay-when-paid cash, governed questions and the specialist team in simulation. Then we’ll talk through your systems and what a first phase would cover.

Prefer email? Write to hello@dideh.ai.

We use these details only to arrange the walkthrough.