What is over and under billing in construction?
The short answer
The gap between what has been billed on a job and the revenue earned under percentage of completion. Overbilling is billing ahead of the work; underbilling is work done but not yet billed. Both appear on the WIP schedule.
An example
Job A: earned $2.0M, billed $2.3M, so it is overbilled $300K. Job B: earned $3.0M, billed $2.6M, so it is underbilled $400K. Earned revenue is percent complete times contract value.
Why it matters to a general contractor
Over and under billing ties the WIP schedule to the balance sheet and to cash. Large underbillings are a warning sign for sureties; large overbillings mean cash collected for work still to be paid for.