What is a pending change order (PCO)?

Also called: PCO, potential change order

The short answer

A change in scope or cost that has been identified but not yet approved by the owner. Until it is signed, the cost may be incurred without the revenue to match.

An example

The superintendent spends $60K on unforeseen rock removal. The PCO is submitted at $72K but not yet signed, so the cost is in job cost and the revenue is not in contract value.

Why it matters to a general contractor

A large pile of pending change orders depresses margin and percent complete and adds to underbilling. Tracking their age and expected approval rate is part of an honest forecast.

Walkthrough

See dideh run a modeled contractor.

We’ll walk you through a fully modeled general contractor, with WIP, pay-when-paid cash, governed questions and the specialist team in simulation. Then we’ll talk through your systems and what a first phase would cover.

Prefer email? Write to hello@dideh.ai.

We use these details only to arrange the walkthrough.