What is a change order in construction?
The short answer
A written change to a contract's scope, price or schedule. Approved change orders adjust contract value; pending or unapproved ones are a common source of margin and cash risk until they are signed.
An example
The owner adds a second elevator. The contractor prices it at $480K and 3 weeks of schedule, the owner signs, and the revised contract value goes from $22.0M to $22.48M.
Why it matters to a general contractor
Change orders are where many jobs make or lose their margin. Work done on changes that haven't been approved is cost without matching revenue, and slow approval also delays billing and cash.