What is contract value?

Also called: Revised contract amount

The short answer

The original contract price plus approved change orders. Revenue on a job is earned against it.

An example

Original contract $18.0M, plus $650K of approved change orders, gives a revised contract value of $18.65M. Pending changes are not included until they are approved.

Why it matters to a general contractor

Contract value is the top line of every job on the WIP schedule. Earned revenue, percent complete and margin are all calculated against it, so including unapproved changes overstates revenue and margin.