How to build and read a WIP schedule.
By Sina Ahmadi, Founder of dideh · Published
The short answer
A WIP schedule lists every open job with its revised contract, estimated total cost, cost to date, percent complete, earned revenue, billings, over or under billing and projected margin. Percent complete is cost to date divided by estimated total cost; earned revenue is revised contract times percent complete; over or under billing is billed to date less earned revenue. Read it for three things each month: jobs whose projected margin moved, jobs that are underbilled, and cost-to-complete estimates that did not change while cost was spent.
What a WIP schedule is for
The WIP schedule is the one report that shows a general contractor’s backlog job by job: how much is left to build, how much has been earned, how much has been billed, and what each job is expected to make. Leadership uses it to manage margin. Lenders and sureties use it to judge whether the company’s revenue and working capital are what they appear to be.
It is also the base of revenue recognition. Under percentage of completion, the revenue on the income statement comes straight from the earned revenue column.
The columns, and how each is calculated
| Column | How it is calculated |
|---|---|
| Revised contract | Original contract + approved change orders |
| Estimated total cost (EAC) | Cost to date + cost to complete, from the project team |
| Percent complete | Cost to date ÷ estimated total cost |
| Earned revenue | Revised contract × percent complete |
| Over / (under) billed | Billed to date − earned revenue |
| Projected gross profit | Revised contract − estimated total cost |
| Projected margin | Projected gross profit ÷ revised contract |
| Fade since bid | Projected margin − bid margin, in points |
Every calculated column depends on one estimate: the cost to complete. If it is stale, percent complete, earned revenue, billing position and margin are all wrong together.
A worked example
| Line | Amount |
|---|---|
| Revised contract | $61.0M |
| Estimated total cost | $52.1M |
| Cost to date | $12.5M |
| Percent complete | 24% |
| Earned revenue | $14.6M |
| Billed to date | $13.7M |
| Under billed | ($0.9M) |
| Projected margin | 14.6%, against 16.0% bid |
This job has already faded 1.4 points at a quarter complete, and it is underbilled by about $0.9M. Either signal alone deserves a question in the WIP review. Together they often mean work done on scope the owner has not yet approved.
How to read it each month
- Margin movement. Compare each job’s projected margin with last month. A job that slips a few tenths every month is fading, even when no single month looks alarming. See profit fade.
- Underbilling. Costs in excess of billings is revenue you have recognized but cannot bill yet. Ask why: unapproved change orders, a billing schedule that lags the work, or an estimate that is too low.
- Overbilling. Billings in excess of costs is healthy in moderation, since it funds the work. Large or growing overbilling on a job near completion can mean costs that have not been recorded yet.
- Stale estimates. If cost to date rose and estimated total cost did not move, the estimate has not been updated, and percent complete is overstated.
- Concentration. Look at which few jobs carry most of the backlog and most of the underbilling. That is where the company’s risk sits.
What lenders and sureties look for
A surety reads the WIP schedule to answer two questions: will these jobs make the money the company says, and does the balance sheet reflect it? So it looks closely at net underbilling, which can inflate earnings and working capital, at fade from one WIP schedule to the next, and at whether the schedule ties to the financial statements. A clean, consistent WIP schedule that ties out every month makes those conversations short.
Free WIP schedule template
The free WIP schedule template has every column above, with the formulas built in, fade and month-over-month change flagged in red, and five sample jobs to replace with your own. It is a spreadsheet you can download and use as it is.
How dideh does it
dideh builds the WIP schedule from the systems a contractor already runs, ties it to the ledger, and forecasts each job’s revenue, margin and cash from the work itself, so a job that is fading or drifting into underbilling shows up the month it starts. See the zero-day close.