How general contractors forecast cash at 13, 26 and 52 weeks.
By Sina Ahmadi, Founder of dideh · Published
The short answer
Build the forecast from the jobs, not from the ledger. For the next 13 weeks, forecast every pay application by job and by the week each owner actually pays, then subtract payroll, subcontractor and vendor payments on their real terms, retainage and debt service. At 26 and 52 weeks the inputs change from billing schedules to backlog burn and weighted pipeline, and the forecast becomes a range rather than a number. Then measure the low point against your cash minimum and score the forecast against what happened every week.
Why a contractor’s cash is hard to forecast
A general contractor can be profitable on every job and still run short of cash, because the timing of money in and money out rarely lines up. Costs are paid weekly or on subcontract terms. Revenue is billed monthly through pay applications, paid by owners on their own schedule, and partly withheld as retainage until the job or a stage of it is complete.
That is why the income statement is a poor guide to cash. Revenue under percentage of completion tells you what was earned; it says nothing about when it will arrive. Underbilling makes the gap wider: work done but not yet billed is revenue on paper and nothing in the bank.
What goes into a 13-week cash forecast
The 13-week cash forecast is the working view: week by week, receipts less payments, starting from today’s bank balance. For a general contractor the lines are:
- Owner receipts, by job. Each upcoming pay application, its expected amount net of retainage, and the week that owner is likely to pay.
- Retainage releases. Only on jobs where completion, or a release milestone, falls inside the 13 weeks.
- Change orders. Approved change orders as billed; pending change orders left out of receipts until signed, even though their cost may already be in payments.
- Payroll. Weekly, from crew plans and project staffing, including burden.
- Subcontractor payments. On each subcontract’s terms, with pay-when-paid tied to the matching owner receipt and retainage held back.
- Vendors and equipment. Material purchase orders and rentals on their payment terms.
- Overhead, debt service and taxes. Rent, insurance, loan payments, estimated taxes and any planned distributions.
The output is the ending cash balance for each week, and its lowest point: the cash low point and the week it falls in.
Build it from the jobs, not the ledger
A forecast that starts from last quarter’s bank activity and rolls it forward will miss exactly the things that move a contractor’s cash: a large job starting, another closing out and releasing retainage, a subcontract buyout that changes payment terms. Start instead from each open job.
For every job, the cost to complete and the schedule say how much work remains and when it will be done. The schedule of values and the billing terms turn that work into pay applications by month. The subcontracts and purchase orders turn the same work into payments. Add the jobs together and you have the company’s receipts and payments, built from the work itself.
This is also why the cash forecast and the WIP schedule should agree. If a job’s cost to complete is wrong, both its margin and its cash forecast are wrong.
Use each owner’s real payment pattern
Contract terms say when an owner should pay. Your receivables history says when they do. Use the history. An owner on 30-day terms who has paid in 45 days on its last ten pay applications belongs in the forecast at 45 days.
The size of the effect is easy to underestimate. Each day later that owners pay holds back about one day of revenue:
| Step | Arithmetic | Result |
|---|---|---|
| One day of revenue | $200M ÷ 365 | about $0.55M |
| Cash held up by 15 days of delay | $0.55M × 15 | about $8.2M |
| Passed on through pay-when-paid (if about two thirds of cost is subcontracted) | $8.2M × 2/3 | about $5.5M |
| Net cash the contractor is short | $8.2M − $5.5M | about $2.7M |
You can run the same arithmetic on your own revenue with the construction cash flow calculator.
26 and 52 weeks: from schedules to ranges
Beyond a quarter, there are fewer pay applications you can name. The 26 and 52 week forecasts rely on different inputs:
- Backlog burn. How signed backlog converts to billing over time, by job, from each schedule.
- Weighted pipeline. Pursuits not yet won, weighted by your win rate for that kind of work, and by when they would start.
- Margin at completion. Each job’s projected margin, including the fade your history says to expect, since lost margin is lost cash.
- Overhead and capital plans. Hiring, equipment, debt maturities and distributions.
Because each of those inputs is uncertain, a 52-week forecast should be a range with a likely value inside it, not a single number. The range should be wider at 52 weeks than at 13, and it should narrow over time as the forecast is scored against what actually happened.
Measure the low point against your cash minimum
The question leadership, lenders and sureties care about is not the ending balance but the lowest one. Compare each week’s forecast with your cash minimum: the least cash you intend to hold, set by leadership or by covenants on your line of credit.
Then stress the forecast. What happens to the low point if your largest owner pays 30 days later? If two jobs fade one point each? If a large pursuit slips a quarter? A forecast that answers those questions before they happen is what lets a CFO draw on the line early, renegotiate terms or hold a distribution, rather than react.
Score the forecast every week
A forecast you never check does not get better. Each week, compare what the forecast said for that week with what the bank shows, and keep the error by horizon: how far off the 13-week view was, the 26-week view, the 52-week view. Look at where the misses came from, usually a specific owner, a job whose schedule moved, or a cost line forecast from a stale estimate, and fix the input rather than adjusting the total.
Common mistakes
- Forecasting receipts on contract terms instead of each owner’s actual payment history.
- Counting pending change orders as cash before they are signed.
- Leaving retainage receivable in the forecast as if it were current.
- Treating pay-when-paid as if it removes the risk, when it only shares the delay and may not pass it all on.
- Building the forecast from the ledger, so it misses jobs starting, closing and changing.
- Giving a single number at 52 weeks with no range around it.
How dideh does it
dideh builds the cash forecast at 13, 26 and 52 weeks from every job’s schedule, cost to complete, billing terms, retainage and pay-when-paid, with each horizon’s likely range and the low point against your cash minimum. Every forecast is scored against what happened. See the zero-day close for how the forecasts are built.