Profit fade: why jobs finish below their bid margin, and how to see it early.

By Sina Ahmadi, Founder of dideh · Published

The short answer

Profit fade is the drop in a job’s margin between the bid and the final result. It usually comes from buyout above the estimate, unapproved change orders, general conditions that run long with the schedule, and labor productivity, and it shows up late because cost to complete is not updated as fast as cost is spent. You can see it early by tracking each job’s margin at completion month by month, watching underbillings and aging change orders, and comparing every live job with similar jobs you have already finished.

What profit fade is

Fade is measured in percentage points of margin. A job bid at a 17% bid margin that finishes at 16% has faded one point. The opposite, a job finishing above its bid margin, is a gain.

One point sounds small. Spread across a company it is not. On $400M of annual revenue, each point of fade is $4M of margin that was in the plan and never arrives as cash. That is why fade belongs in the cash forecast as well as the income statement.

Where fade comes from

Fade is rarely one event. It is usually several small ones on the same job:

  • Buyout above the estimate. Subcontracts and purchase orders awarded at more than the estimate carried. Buyout is the first chance to find fade, before work starts.
  • Scope without a signed change order. Work done on a pending change order has its cost in the job and none of its revenue until the owner signs, and some never are.
  • Schedule slips. Every extra month on site costs a month of general conditions: supervision, temporary facilities, insurance and project staff.
  • Labor productivity. Self-performed work installed at more hours per unit than estimated.
  • Estimate gaps. Scope missed or underpriced at bid, which no amount of project management recovers.
  • Closeout costs. Punch list, warranty work and rework at the end of the job, when there is little revenue left to absorb them.

Why fade shows up late

Under percentage of completion, a job’s margin is only as good as its estimate at completion, which is cost to date plus cost to complete. If the cost to complete is left at the original estimate while cost to date climbs, two things happen. The job looks further along than it is, so it recognizes more revenue. And the margin stays at the bid number, until the remaining budget runs out and the fade lands all at once, often in the last stretch of the job.

The longer it waits, the less anyone can do about it. Fade found at buyout can be bought back. Fade found at 90% complete can only be reported.

Early signals in the WIP schedule

The WIP schedule already contains most of what you need. Look for these on every job, every month:

  • Margin at completion moving. A job’s projected margin at completion that slips a little each month is fading, even if no single month looks alarming.
  • Cost to complete that does not move. If cost to date rises and the cost to complete stays the same, the estimate has not been updated.
  • Growing underbillings. Rising costs in excess of billings can mean work done that cannot be billed, often because it is unapproved scope.
  • Aging pending change orders. The older a pending change order, the less likely it is to be signed at full value.
  • General conditions ahead of schedule. General conditions spent faster than the schedule is progressing.
  • Buyout variance. Subcontracts and purchase orders awarded against the estimate, line by line.
Illustration: one job’s projected margin, month by month
MonthPercent completeMargin at completionChange from bid
Bid0%17.0%—
Month 320%16.8%−0.2 pts
Month 645%16.5%−0.5 pts
Month 970%16.1%−0.9 pts
Final100%15.9%−1.1 pts

In this illustration the fade was visible by month 3 and clear by month 6, when there was still more than half the job left to act on it.

Measure fade across your own jobs

Fade on one job is a problem to solve. Fade across many jobs is a pattern to learn from. Once every closed job has its bid margin and final margin side by side, you can see fade by project type, by client, by project manager, by region and by contract size. That tells you where to bid more carefully, which owners’ jobs tend to grow scope without paying for it, and what fade to expect on a job today. See measuring every job against your own history.

A monthly fade review

  1. Have project managers update cost to complete on every job before the WIP review, not after.
  2. List every job whose margin at completion moved since last month, with the reason.
  3. Review pending change orders by age and value, and decide which to escalate with the owner.
  4. Compare general conditions spent with schedule progress.
  5. Compare each live job’s margin path with similar finished jobs at the same percent complete.
  6. Carry the expected fade into the revenue, margin and cash forecast.

How dideh does it

dideh measures every job against the company’s own history and forecasts margin from the work itself, so a job that is fading shows up in the month it starts, not the month it closes. See the zero-day close, or run the effect of a point of fade on your own cash with the cash flow calculator.

Newsletter

Construction finance, worked through.

New articles, templates and calculators for general contractor CFOs, by email when they come out.

New articles and templates from dideh. Reply to any email to stop.

Walkthrough

See dideh run a modeled contractor.

We’ll walk you through a fully modeled general contractor, with WIP, pay-when-paid cash, governed questions and the specialist team in simulation. Then we’ll talk through your systems and what a first phase would cover.

Prefer email? Write to hello@dideh.ai.

We use these details only to arrange the walkthrough.