What is margin at completion?
Also called: Projected margin
The short answer
The margin a job is expected to earn when finished: contract value less estimate at completion, divided by contract value. Tracked month by month, it shows fade before the job closes.
An example
Contract value is $10.6M and estimate at completion is $9.3M, so projected margin at completion is $1.3M, or 12.3%. Last quarter it was 13.5%, so the job is fading about 0.4 points a month.
Why it matters to a general contractor
Margin at completion is the number to watch month by month. Its trend shows fade early, and it is the basis for the projected gross profit that sureties and lenders read on the WIP schedule.