What is margin at completion?

Also called: Projected margin

The short answer

The margin a job is expected to earn when finished: contract value less estimate at completion, divided by contract value. Tracked month by month, it shows fade before the job closes.

An example

Contract value is $10.6M and estimate at completion is $9.3M, so projected margin at completion is $1.3M, or 12.3%. Last quarter it was 13.5%, so the job is fading about 0.4 points a month.

Why it matters to a general contractor

Margin at completion is the number to watch month by month. Its trend shows fade early, and it is the basis for the projected gross profit that sureties and lenders read on the WIP schedule.

Walkthrough

See dideh run a modeled contractor.

We’ll walk you through a fully modeled general contractor, with WIP, pay-when-paid cash, governed questions and the specialist team in simulation. Then we’ll talk through your systems and what a first phase would cover.

Prefer email? Write to hello@dideh.ai.

We use these details only to arrange the walkthrough.