What is estimate at completion (EAC)?

Also called: EAC, projected final cost

The short answer

The expected total cost of a job when finished: cost to date plus cost to complete. Compared with contract value, it gives the projected margin at completion.

An example

Cost to date is $6.2M and cost to complete is $3.1M, so EAC is $9.3M. On a $10.6M contract, that gives a projected margin of ($10.6M − $9.3M) ÷ $10.6M ≈ 12.3%.

Why it matters to a general contractor

EAC drives percent complete, earned revenue and projected margin. A change to it moves every one of those numbers, so how it is updated each month matters a great deal.