What is cost to complete?
Also called: CTC
The short answer
The cost still to be spent to finish a job. Added to cost incurred to date, it gives the estimate at completion, so an accurate cost to complete is what keeps WIP and margin forecasts honest.
An example
A job has $6.2M of cost to date. The project manager's line-by-line review shows $3.1M still to spend, so cost to complete is $3.1M and the estimate at completion is $9.3M.
Why it matters to a general contractor
Cost to complete is the most judgment-heavy number in construction accounting. If it is too low, percent complete runs ahead, revenue and margin are overstated, and the correction shows up later as fade.