What is profit fade in construction?
Also called: Profit fade, margin fade
The short answer
The drop in a job's margin between bid and completion, in percentage points. A job bid at 17% that finishes at 16% faded one point. Fade spread across a contractor's jobs is one of the largest hidden costs in construction.
An example
A $10M job was bid at 17% margin ($1.7M). Six months in, the projected margin is 14%. That is 3 points of fade, or $300K of profit gone. Across a $200M portfolio, one point of average fade is $2M.
Why it matters to a general contractor
Fade usually builds slowly and is recognized late, because cost to complete is updated optimistically. Tracking projected margin month by month against bid catches the trend while there is still time to recover through change orders, buyout or schedule.