What is buyout in construction?

The short answer

Awarding the subcontracts and major purchase orders on a job after the prime contract is signed. Buying out below the estimate creates buyout savings; buying out above it erodes margin before work starts.

An example

The estimate carried $2.4M for mechanical. The general contractor awards the mechanical subcontract for $2.25M, a $150K buyout saving. If it had to award at $2.55M, the job would lose $150K of margin before work started.

Why it matters to a general contractor

Buyout is the first point where a job's margin actually changes. Tracking buyout savings and losses by trade shows whether estimates are realistic and whether savings are being kept in contingency or quietly spent.

Walkthrough

See dideh run a modeled contractor.

We’ll walk you through a fully modeled general contractor, with WIP, pay-when-paid cash, governed questions and the specialist team in simulation. Then we’ll talk through your systems and what a first phase would cover.

Prefer email? Write to hello@dideh.ai.