What is buyout in construction?
The short answer
Awarding the subcontracts and major purchase orders on a job after the prime contract is signed. Buying out below the estimate creates buyout savings; buying out above it erodes margin before work starts.
An example
The estimate carried $2.4M for mechanical. The general contractor awards the mechanical subcontract for $2.25M, a $150K buyout saving. If it had to award at $2.55M, the job would lose $150K of margin before work started.
Why it matters to a general contractor
Buyout is the first point where a job's margin actually changes. Tracking buyout savings and losses by trade shows whether estimates are realistic and whether savings are being kept in contingency or quietly spent.