What are general conditions in construction?

The short answer

Job-level costs that are not tied to a specific scope of work, such as site supervision, temporary facilities, insurance and project staff. Running longer than scheduled usually means general conditions over budget.

An example

A job's general conditions budget is $95K a month for 14 months: superintendent, project manager, trailer, temporary power and insurance. If the job runs 3 months late, that is about $285K over budget even if every trade comes in on cost.

Why it matters to a general contractor

General conditions are tied to time, so schedule slips go straight into cost. They are one of the most common sources of fade on jobs that run long.

Walkthrough

See dideh run a modeled contractor.

We’ll walk you through a fully modeled general contractor, with WIP, pay-when-paid cash, governed questions and the specialist team in simulation. Then we’ll talk through your systems and what a first phase would cover.

Prefer email? Write to hello@dideh.ai.

We use these details only to arrange the walkthrough.