What is a schedule of values?
Also called: SOV
The short answer
The breakdown of a contract's price into line items of work, agreed with the owner, against which progress is billed in each pay application.
An example
A $12M contract's schedule of values lists general conditions $1.1M, site work $0.9M, concrete $2.4M, steel $1.8M and so on. Each pay application bills percent complete against each line.
Why it matters to a general contractor
The schedule of values sets how quickly a job can bill. A front-loaded SOV can help cash early in the job; owners and lenders watch for SOVs that bill ahead of the work.