What is retainage in construction?
Also called: Retention
The short answer
A percentage of each payment, often 5% to 10%, that the owner holds back until the job, or a defined stage, is complete. Contractors usually hold back the same from subcontractors, and retainage receivable can be a large part of cash tied up.
An example
On a $4M contract with 10% retainage, a $400K pay application is paid at $360K and $40K is held. By completion the owner may be holding $400K, often released months after substantial completion.
Why it matters to a general contractor
Retainage is earned cash with a late, uncertain date. Across all open jobs it is often one of the largest blocks of cash a contractor is waiting on, which is why it belongs in the cash forecast job by job.