What is job cost?
The short answer
Costs recorded against a specific job and cost code: labor, materials, subcontracts, equipment and general conditions. It is the base for WIP and for every margin measure.
An example
A job's cost report shows labor $1.2M, materials $0.8M, subcontracts $5.6M, equipment $0.3M and general conditions $0.9M, each against its cost code and budget. Together that is $8.8M of job cost to date.
Why it matters to a general contractor
Job cost is the source for WIP, percent complete and every margin measure. If costs are coded late or to the wrong job, revenue and margin on both jobs will be wrong.